APPENDIX A: DCC SERVICES – TECHNICAL CALCULATIONS (PARKS PROGRAM)

Technical schedules supporting the proposed Parks DCC program, including project costs, benefit allocations, municipal assistance, and rate calculations.

17.4 BYLAW NO. 2291 (First, Second and Third Readings)

Key facts

  • Total project cost: $51,214,473
  • DCC recoverable amount: $48,227,328
  • Total municipal responsibility: $2,987,145
  • Existing DCC reserve monies: $14,440,721
  • Calculated DCC per person: $844.09

APPENDIX A: DCC SERVICES – TECHNICAL CALCULATIONS (PARKS PROGRAM)

Appendix A divider page graphic
Appendix A divider page graphic
Page 22–26

PARKS DEVELOPMENT COST CHARGE BYLAW UPDATE

This page is intentionally blank.

Page 22–26

CITY OF LANGFORD

PARKS IMPROVEMENTS AND ACQUISITION DCC PROGRAM

PARKLAND IMPROVEMENTS

DCC Project ID Project Name Description/Extent Cost Estimate (2026 $; includes contingency) Benefit Factor Benefit to New Development Municipal Assist Factor (1%) DCC Recoverable Total Municipal Responsibility
P1 Irwin Trail Phase 1; project is completed but not on DCC list $445,172 100% $445,172 $4,452 $440,720 $4,452
P2 Lakepoint Park Project is completed but not on DCC list $354,066 100% $354,066 $3,541 $350,525 $3,541
P3 Irwin Trail Phase 2; work underway with expected completion of Summer 2026 $550,000 100% $550,000 $5,500 $544,500 $5,500
P4 Phase 12 Park Concept design provided to City; target completion mid-2027 $1,100,000 100% $1,100,000 $11,000 $1,089,000 $11,000
P5 Sooke Lake Road Park Park Development $5,000,000 50% $2,500,000 $25,000 $2,475,000 $2,525,000
P6 Totangi Trail Development Trails and Furnishings (e.g., garbage cans and benches) $132,300 100% $132,300 $1,323 $130,977 $1,323
P7 Olympic View Trail Development Trails and Furnishings (e.g., garbage cans and benches) $266,700 100% $266,700 $2,667 $264,033 $2,667
P8 Weir Langdon Trail Development Trails and Furnishings (e.g., garbage cans and benches) $209,118 100% $209,118 $2,091 $207,027 $2,091
P9 Accessible Playground Equipment $50k/year for 5 years; Park Development and Construction for Accessible Playground Equipment $250,000 100% $250,000 $2,500 $247,500 $2,500
P10 Hiking Trails Improvements Park Development $100,000 100% $100,000 $1,000 $99,000 $1,000
P11 BMP Gateway Park Near Riviera Road; Park Development $250,000 100% $250,000 $2,500 $247,500 $2,500
P12 Skirt Mtn Future Phases Park Development $150,000 100% $150,000 $1,500 $148,500 $1,500
P13 Centennial Park Improvements Irrigation Improvements $385,000 100% $385,000 $3,850 $381,150 $3,850
P14 Veterans Memorial Park (Acquisition and Expansion) Park Development; to be completed in 2026 $2,400,000 100% $2,400,000 $24,000 $2,376,000 $24,000
P15 Langford Gravity Zone and Nature Trails Excludes Bike Track itself; Park Development; Destination Park $750,000 100% $750,000 $7,500 $742,500 $7,500
P16 Thetis and Millstream Parkland Improvements Improvements to develop newly acquired parkland at Thetis and Millstream Park (landscaping, furnishings, lighting). $1,500,000 100% $1,500,000 $15,000 $1,485,000 $15,000
P17 Mill Hill Parkland Improvements Improvements to develop newly acquired parkland at Mill Hill Park (Iandscaping, furnishings, lighting). $700,000 100% $700,000 $7,000 $693,000 $7,000
P18 Langford/Glen Lake Parkland Improvements Improvements to develop newly acquired parkland at Langford/Glen Lake Park (landscaping, furnishings, lighting). $1,000,000 100% $1,000,000 $10,000 $990,000 $10,000
P19 Goldstream Meadows Parkland Improvements Improvements to develop newly acquired parkland at Goldstream Meadows Park (landscapting, furnishings, lighthing). $700,000 100% $700,000 $7,000 $693,000 $7,000
P20 South Langford Parkland Improvements Improvements to develop newly acquired parkland at South Langford Park (landscaping, furnishings, lighting). $700,000 100% $700,000 $7,000 $693,000 $7,000
P21 Woodlands Park Improvements Improvements to develop newly acquired parkland at Woodlands Park (landscaping, furnishings, lighting). $3,000,000 100% $3,000,000 $30,000 $2,970,000 $30,000

PARKLAND ACQUISITION

DCC Project ID Project Name Description/Extent Cost Estimate (2026 $; includes contingency) Benefit Factor Benefit to New Development Municipal Assist Factor (1%) DCC Recoverable Total Municipal Responsibility
P22 Langford Gravity Zone Parkland Acquisition Secure additional lands for the Langford Gravity Zone park. $6,750,000 100% $6,750,000 $67,500 $6,682,500 $67,500
P23 Parkland Acquisition - Community Secure additional lands (1 ha) City-wide for Community Parks. $7,907,372 100% $7,907,372 $79,074 $7,828,298 $79,074
P24 Parkland Acquisition - Neighbourhood (North Langford) Secure additional lands (1 ha) in North Langford for Neighbourhood Parks. $7,907,372 100% $7,907,372 $79,074 $7,828,298 $79,074
P26 Parkland Acquisition - Neighbourhood (South Langford) Secure additional lands (1 ha) in South Langford for Neighbourhood Parks. $7,907,372 100% $7,907,372 $79,074 $7,828,298 $79,074
P27 Parkland Acquisition - Waterfront Secure additional lands (0.25 ha) along Langford Lake and Glen Lake. $800,000 100% $800,000 $8,000 $792,000 $8,000
TOTALS $51,214,473 $48,714,473 $487,145 $48,227,328 $2,987,145
Page 22–26

CITY OF LANGFORD

PARKS DCC RATE CALCULATION

A: Parks DCC Calculation

Land Use Estimated New Development (Col. (1)) Unit (Col. (2)) Person per unit (residential)/Equivalent Population/m2 (other land uses) (Col. (3)) Equivalent Population (Col. (4) = (1) x (3)) % Population Equivalent (Col. (5) = (4) / (a))
One-Family Dwelling (<400m2) 225 Dwelling Unit/ Lot 2.600 585 1%
One-Family Dwelling (>400m2) 225 Dwelling Unit/ Lot 4.200 945 2%
Two-Family Dwelling 450 Dwelling Unit 2.600 1,170 3%
Townhouse 1,500 Dwelling Unit 2.600 3,900 10%
Apartment 12,600 Dwelling Unit 1.800 22,680 57%
Commercial Use or Industrial Use 591,146 m2 Gross Floor Area 0.018 10,747 27%
Total Equivalent Population 40,027 (a) 100%
Calculation Amount
Net Parks DCC Program Recoverable $48,227,328 (b)
Existing DCC Reserve Monies $14,440,721 (c)
Net Amount to be Paid by DCCs $33,786,607 (d) = (b) - (c)
DCC per Person $844.09 (e) = (d) / (a)

B: Unit Parks DCC Calculation

C: Resulting Parks DCCs

DCC Revenue Estimates
Land Use DCC Rate Unit Calculation DCC Revenue Estimate
One-Family Dwelling (<400m2) $2,195 Per Dwelling Unit/ Lot (e) x Col. (3) $493,796
One-Family Dwelling (>400m2) $3,545 Per Dwelling Unit/ Lot (e) x Col. (3) $797,670
Two-Family Dwelling $2,195 Per Dwelling Unit (e) x Col. (3) $987,591
Townhouse $2,195 Per Dwelling Unit (e) x Col. (3) $3,291,970
Apartment $1,519 Per Dwelling Unit (e) x Col. (3) $19,144,072
Commercial Use or Industrial Use $15.35 Per m2 Gross Floor Area (e) x Col. (3) $9,071,509
Page 22–26
Extracted from: City of Langford Parks DCC Background Report