Staff Report to Special Council: BC Active Transportation Infrastructure Grant
Report regarding the BC Active Transportation Infrastructure Grant program (application/award and related project details).
Key facts
- Report located at pages 65-67 as agenda item 7.4
- Relates to BC Active Transportation Infrastructure Grant (program details, project scope and/or funding authorization)
- Intended action: information and/or approval to apply for or accept funding (specific dollar amounts and project details in attachment)
Staff Report to Special Council: BC Active Transportation Infrastructure Grant
t 250.478.7882
e administration@langford.ca
2nd Floor, 877 Goldstream Avenue
Langford, BC V9B 2X8
DATE
Monday, November 21, 2022
DEPARTMENT
Engineering
SUBJECT
BC Active Transportation Infrastructure Grant
BACKGROUND
The City of Langford, through the Engineering Department, routinely applies for infrastructure grants to extend sidewalks or multi-use trails. The purpose of this report is to gain Council approval for the City to submit a grant application to the current intake of the BC Active Transportation Infrastructure Grant.
COMMENTARY
The BC Active Transportation Infrastructure fund is for “shovel ready” projects. In general terms, a shovel ready project is one where the vast majority of the detailed design is complete, and the project is ready to tender.
In 2020, the City applied to the BC Active Transportation Infrastructure grant for the Bellamy Road Multi-Use path but was unsuccessful obtaining a grant that year. With the designs for the Bellamy Road Multi-Use path already in-house, staff chose to apply for this grant again with revised pricing on the estimates. The grant was submitted in October 2022.
A project location diagram is provided on the following page.


Staff are looking for a resolution from Council in support of the BC Active Transportation Infrastructure grant for the Bellamy Road Multi-Use path. A formal resolution supporting this application is due by mid-December 2022.
FINANCIAL IMPLICATIONS
The estimated cost of the project is $880,680.00 plus GST and includes a 20% contingency (the maximum allowable contingency for the application).
If successful, the grant provides 50% funding for the project. Staff are suggesting the remaining 50% matching funds be provided through the City’s Gas Tax funding. Each year staff allocate gas tax to provide for a matching grant. This is money allocated through the Engineering Department budget as the “multi use trail” budget.
Gas Tax funds are generally delivered to communities twice a year by upper levels of government, late July and early December and can be invested across prescribed project categories to address local priorities.
LEGAL IMPLICATIONS
None noted.
OPTIONS
Option 1
THAT Council direct staff to apply to the BC Active Transportation Infrastructure Application for 2022/2023 for the Bellamy Road Multi-Use Path at an estimated cost of $880,680.00 plus GST; and
THAT Council direct staff to include this project in the 2023 Capital Plan, pending approval of the grant, and fund the City’s 50% share of the estimated project cost using Gas Tax funds.
OR
Option 2
THAT Council not apply for a BC Active Transportation Infrastructure grant at this time.
SUBMITTED BY
Michelle Mahovlich, P.Eng, P.Geo, Director of Engineering and Public Works
Concurrence:
Donna Petrie, Senior Manager of Business Development and Events
Concurrence:
Will Ying-udomrat, Manager of Legislative Services
Concurrence:
Matthew Baldwin, MCIP, RPP, Director of Planning and Subdivision
Concurrence:
Michael Dillabaugh, CPA, CA, Director of Finance
Concurrence:
Marie Watmough, Deputy Director of Corporate Services
Concurrence: Braden Hutchins, Director of Corporate Services
Concurrence:
Darren Kiedyk, Chief Administrative Officer