DocumentsStaff ReportJul 15, 2019Pages 128–130
Staff Report - Pre-Award of Humpback Irwin Road Multi-Use Trail Connector (Engineering)
Engineering staff report recommending pre-award action for construction of the Humpback Irwin Road multi-use trail connector, including cost estimates and procurement recommendations.
Key facts
- Project: Humpback Irwin Road Multi-Use Trail Connector
- Action: Pre-award recommendation with procurement next steps
- Financials: cost estimates provided (detailed figures in report)
Staff Report - Pre-Award of Humpback Irwin Road Multi-Use Trail Connector (Engineering)
2nd Floor · 877 Goldstream Avenue · Langford, BC Canada · V9B 2X8
T · 250-478-7882 F · 250-478-7864
Date:
July 15, 2019
Department:
Engineering
Subject:
Pre-Award of Humpback Irwin Road Multi-Use Trail Connector
Background
The City received a Bike BC grant for the completion of the Humpback Irwin Road Trail Connector. This is a paved multi-use path connecting the pathway near the Westhills Play Park/West Shore Parkway through Irwin Park, out onto Irwin Road, adjacent to Irwin Road and then north up Humpback Road all the way to Sooke Lake Road. The purpose of this report is to seek Council pre-approval to award to the lowest compliant bidder for the completion of the Bike BC project.
A project drawing is attached to this report.
Commentary
The City has tendered the project on BC Bid and anticipates closing the tender on or about July 18th, 2019.
Staff are asking that Council pre-approve award of the construction project to the lowest compliant bidder within the project budget.
Financial Implications
The project is funded 50% by the Bike BC grant and 50% by Gas Tax Funds. The total projected cost of the project including engineering fees is $1,373,975.00.
Legal Implications
None noted.
Options
That Council:
- Direct staff to award the Humpback Irwin Multi-Use Trail Connector construction project to the lowest compliant bidder;
OR
- Not award the Humpback Irwin Multi-Use Trail Connector construction project at this time
Respectfully submitted,
Submitted by:
Michelle Mahovlich, P.Eng, P.Geo, Director of Engineering
Concurrence:
George Henshall, AScT., Deputy Director of Engineering and Public Works
Concurrence:
Adriana Proton, Manager of Legislative Services
Concurrence:
Matthew Baldwin, MCIP, RPP Director of Planning
Concurrence:
Chris Aubrey, Fire Chief
Concurrence:
Cory Manton, Manager of Parks and Recreation
Concurrence:
Michael Dillabaugh, CPA, CA, Director of Finance
Concurrence:
Braden Hutchins, Director of Corporate Services
Concurrence:
Darren Kiedyk, Chief Administrative Officer
:mm
Attachment: Project Drawing
