Key facts

  • Tender low bidder listed: Scansa Construction Ltd. ($5,539,693.14 in summary table)
  • Recommended award: Scansa Construction Ltd. for $4,952,771.78 plus GST (report text)
  • Provisional items: Waterworks in Segment 4 ($359,815.76, to be paid by Westhills) and optional street lighting ($227,105.60)
  • Funding: Development Cost Charge Program plus New Building Canada Infrastructure Grant (2/3 funding)

Staff Report: West Shore Parkway Segment 3 and 4 Tender Award

2nd Floor · 877 Goldstream Avenue · Langford, BC Canada · V9B 2X8
T · 250-478-7882 F · 250-478-7864

Date:

May 16, 2016

Department:

Engineering

Subject:

West Shore Parkway Segment 3 and 4 Tender Award

Background

The purpose of this report is to inform Council of the West Shore Parkway Segment 3 and 4 tender results and receive approval to award the contract.

Commentary

The West Shore Parkway is being designed to connect the Trans-Canada Highway through the currently constructed West Shore Parkway to Highway 14/ Sooke Road; it is divided into nine (9) Segments that are designed and tendered separately from each other. Segment 3 and 4 of the West Shore Parkway is the middle section, connecting to Segment 2 (Glenshire Business Park) and Westhills (Segment 5)

A total of six (6) contractors submitted bids for this project; a summary of the bids is presented below.

A bid summary was completed by Associated Engineering which was reviewed by engineering staff. After review, engineering staff are recommending that the contract be awarded to the low bidder, Scansa Construction Ltd.

Tender Summary

Tenderer Total Tender Price
Scansa Construction Ltd. $5,539,693.14
Windley Contracting Ltd. $5,730,015.00
Milner Group $6,055,278.80
Don Mann Excavating $6,227,449.70
Jacob Bros $6,306,999.00
Dawson Construction Ltd. $6,398,481.00

Financial Implications

The tender included two provisional items:

  1. Waterworks in Segment 4 to be paid for by Westhills – $359,815.76. Langford will invoice Westhills. Westhills has agreed for Scansa Construction Ltd to construct these works.

  2. Street lighting – $227,105.60. Optional street lighting was requested in order to assess the net value of standalone lights versus lights mounted on utility poles. This is subject to the overall budget of the West Shore Parkway project.

The West Shore Parkway Segment 3 and 4 construction will be funded through the City’s Development Cost Charge Program with an additional 2/3 funding coming from the New Building Canada Infrastructure Grant Fund.

Legal Implications

None.

Options

That Council:

  1. Award the contract for Segment 3 and 4 of the West Shore Parkway to Scansa Construction Ltd for a price of $4,952,771.78 plus GST and fund this from the City’s New Building Canada Infrastructure Grant; plus award the optional waterworks to Scansa $359,815.76 plus GST which will be paid by Westhills; and not award the optional street lighting as this will be subject to the overall budget of the West Shore Parkway project.

OR

  1. Not award the contract at this time.

Respectfully Submitted

Submitted by:
Kevin Bowbyes, AScT, Engineering Technologist

Concurrence:
Victor Chen, AScT, Manager of Engineering Construction

Concurrence:
Matthew Baldwin, MCIP, RPP, Director of Planning

Concurrence:
Jane Waters, Parks Planner

Concurrence:
Michelle Mahovlich, P.Eng, P.Geo, Director of Engineering

Concurrence:
Steve Ternent, Director of Finance

Concurrence:
Jim Bowden, Chief Administrative Officer

:kb

Attachment: Associated Engineering verification document

Page 32–35
Extracted from: 20160516-Agenda-Package(108 pages total)