Lake Ida Ann drain replacement

The project would replace a collapsed drain culvert and overflow culverts between Lake Ida Ann and Ashley Place. Construction was estimated at $130,000, funded from the city’s culverts and drainage budget, and needed to meet a fisheries work-window deadline.

Where it stands: Conditional authority to award to the lowest compliant bidder given May 16, 2016; award not recorded.

The site today: Lake Ida Ann drain replacement
The site today · from the staff report · View report

Timeline

Every time this matter appeared in council records, newest first.

  1. May 16, 2016· Council

    Conditional authority granted to award drain replacement contract

    Awarded the Lake Ida Ann Drain Replacement project to the lowest bidder assuming the bid is within the project budget, using funds from the Miscellaneous Culverts & Drainage budget.

    Decision: Authorized awarding Lake Ida Ann Drain Replacement to lowest compliant bidder, subject to budget.