This site is in beta — data may be incomplete and features are still being added.

MattersTransportationFirst seen Apr 15, 2019

Irwin Road trail realignment

Approved

A 3-metre-wide asphalt trail was planned along Irwin Road between Meridian Road and 2955 Irwin Road, alongside a road realignment, crosswalk and pedestrian landing at Meridian. The estimated $60,000 cost was to come from road development charges.

Where it stands: Trail design and installation approved Apr 15, 2019, with an estimated $60,000 from road development charges.

Proposed layout: Irwin Road trail realignment
Proposed layout · from the staff report · View report

Timeline

Every time this matter appeared in council records, newest first.

  1. April 15, 2019· Council

    Council approves Irwin Road trail, road realignment and crosswalk

    Council approved design and installation of a realignment and 3.0m asphalt trail on Irwin Road at an estimated cost of $60,000 funded from Road DCCs.

    Decision: Approved Irwin Road 3.0m asphalt trail realignment and crosswalk at estimated $60,000 from Road DCCs.

    Passed