## AI-processed summary

Staff report (Parks and Recreation) updating the Committee on the planned renovation and expansion of Porcher Park (City Centre) including public engagement results, design/RFP work, community garden plans, and anticipated construction timing.

## Extracted text

### Porcher Park Capital Improvements Update

Source pages: 4–7

## Porcher Park Capital Improvements Update

t 250.478.7882  
e administration@langford.ca  
2nd Floor, 877 Goldstream Avenue  
Langford, BC V9B 2X8

DATE: Tuesday, May 28, 2024  
DEPARTMENT: Parks and Recreation  
SUBJECT: Porcher Park Capital Improvements Update

### Executive Summary

Source pages: 4–7

## Executive Summary

As part of the approved 2024 Capital budget, the City will be renovating and expanding Porcher Park, located in Langford’s City Centre at 822 Wren Place.

Staff presented a draft plan to the public via an onsite open house as well as an online survey. The results of the public engagement process showed strong support for the plan as presented, especially regarding the inclusion of a community garden.

Staff are working on a final design and grading plan that will form part of the Request for Proposal (RFP) for construction of the park. A separate RFP has been issued for the playground equipment and associated surfacing.

Additionally, staff are working on a Community Garden Policy and supporting guidelines and will be bringing these forward to Council prior to issuing a Request for Expression of Interest (RFEI) for the operation of a community garden at this location. It is the City’s expectation that one or more local groups incorporated under the BC Society Act will submit a proposal to oversee a community garden at Porcher Park.

With the exception of the community gardens, the renovated park is anticipated to open in the Fall.

### Background

Source pages: 4–7

## Background

Porcher Park was dedicated to the City by the Porcher family in 1971. As the park was bordered by single family homes, access to the park was limited to an easement over the adjoining lots on Wren Place. The easement area contained a number of large trees that made using the easement challenging, leaving the park underutilized.

Over the last several years, the City has acquired three properties on either side of the existing parkland (two on Wren Place and one on Brock Avenue) with the intention of expanding the park’s size and improving access.

### Commentary

Source pages: 4–7

## Commentary

The expansion of Porcher Park came from the recognition that additional green space was required in the City Centre with the ongoing development and an influx of new residents occupying multi-family residential buildings. This expansion has been in the works since the first property (851 Brock Avenue) was purchased in 2019, while 826 and 830 Wren Place were purchased in 2023.

More recently, and in collaboration with the Greater Victoria Green Team and the Langford Fire Rescue FireSmart program, the Parks, Recreation and Facilities department has held several clean up events at Porcher Park. Invasive species and woody debris were removed from the site and awareness was raised about wildfire safety practices. The expanded Porcher Park has already provided a number of community participation opportunities, and with addition of park amenities, it will continue to provide new opportunities for the residents of the area.

The park concept plan includes forest restoration, planting of shrub beds with a focus on pollinator species, installing interpretive signage highlighting focal points of the park and its ecosystem at work, building a children’s playground including accessible play features, installing a community garden, and creating passive green space areas.

[Image 1: Porcher Park concept plan/site rendering]

An onsite open house was held at Porcher Park on Saturday, April 13th and staff spoke with approximately 30 residents. An online survey was also shared on the “Lets Chat Langford” public engagement platform with over 250 responses received. In addition, an informational postcard with the survey link was mailed to occupants living within 100 metres of the park (approximately 350 residences).

The results of the public engagement process indicate strong support for the draft park plan. A few key findings from the engagement process include:
- a) 41% of respondents live in Langford’s City Centre.
- b) 51.5% of respondents identified a natural wood play structure as a playground preference. There was also strong support for an accessible play feature.
- c) 75.6% of respondents are in support of Porcher Park being the location of a community garden.

Staff are working with the park designer to finalize a drawing as well as a grading plan of the site that will form part of the RFP for the park construction. A separate RFP has been issued for the playground equipment and surfacing.

### Community Garden Operations

Source pages: 4–7

## Community Garden Operations

Staff are working on a policy and supporting guidelines for the operation of the community garden which will then form the basis of a Request For Expressions of Interest from community groups to manage the operation of the community garden areas. Subject to interest from community groups, it is anticipated that the operator will be in place in time to have the gardens available for the 2025 season.

The specifics of the community garden operations and administration as well as the associated policy and guidelines have not yet been finalized; that report and policy will be coming forward at a separate meeting.

Construction of the park is anticipated to start in June, with anticipated completion this fall.

### Financial Implications

Source pages: 4–7

## Financial Implications

- The approved Capital budget for the Porcher Park project is $550,000, which is funded by Park Improvement DCC’s.
- Staff will utilize a portion of the Disability and Access Improvements Capital budget ($100,000) for an accessible piece of playground equipment and rubber surfacing.
- $40,000 has been budgeted in 2024 for community gardens, which will be used to fence and irrigate the area.

### Legal Implications

Source pages: 4–7

## Legal Implications

Staff are recommending the recently acquired properties be dedicated as Park as opposed to retained as amenity lots to ensure the use of the land is preserved as greenspace. A report regarding the dedication will be brought to Council for necessary approvals.

### Strategic Plan Initiatives

Source pages: 4–7

## Strategic Plan Initiatives

This park renovation is in accordance with Langford’s Strategic Plan 2023-2027, Strategic Priority Two: Climate Change and Environmental Stewardship 2c “Review and Action the Food Security Policy as Detailed in the OCP”. This priority is being addressed through the inclusion of a community garden initiative, something that has not been piloted in Langford since 2011.

Additionally, the park renovation also addresses Strategic Priority Six: Quality of Life, Item 6l “increased access to recreation infrastructure and services”, as the renovation and expansion of Porcher Park will increase its accessibility to all Langford residents.

### Options

Source pages: 4–7

## Options

Option 1  
THAT the Community Advisory Committee receive the report for information.

### Submitted By

Source pages: 4–7

## Submitted By

SUBMITTED BY: Wolfgang Schoenefuhs, Parks Planning Coordinator

### Concurrence
- Yari Nielsen, Director of Parks, Recreation and Facilities  
- Donna Petrie, Senior Manager of Communications & Economic Development  
- Matthew Baldwin, RPP, MCIP, Director of Development Services  
- Leah Stohmann, RPP, MCIP, Director of Community Planning and Climate Change  
- Katelyn Balzer, P.Eng., Director of Engineering and Public Works  
- Michael Dillabaugh, CPA, CA, Director of Finance  
- Marie Watmough, Deputy Director of Corporate Services  
- Braden Hutchins, Director of Corporate Services  
- Darren Kiedyk, Chief Administrative Officer