DocumentsStaff ReportMay 1, 2023Pages 122–128
Staff Report: Peatt Road DCC Project - Utility Pole Removal
Staff report regarding the Peatt Road Development Cost Charge (DCC) project and the removal of utility poles as part of the project works.
Key facts
- Project location referenced: Peatt Road
- Subject: DCC project and removal of utility poles
- Listed as agenda item 9.4 for Council consideration on May 1, 2023
Staff Report to Council
t 250.478.7882
e administration@langford.ca
2nd Floor, 877 Goldstream Avenue
Langford, BC V9B 2X8
DATE: Monday, May 1, 2023
DEPARTMENT: Engineering
SUBJECT: Peatt Road DCC Project – Utility Pole Removals
BACKGROUND
The purpose of this report is to inform Council of the status of utility poles in the road right-of-way, that were “topped” by BC Hydro but not fully removed, remaining an unsightly hazard in the roadway.
Peatt Road (from the intersections at Goldstream Avenue and Hockley Avenues inclusive) is currently in the City of Langford Road Development Cost Charge (DCC) Project Program. Figure 1 is a snippet from the Road DCC Program Project Map (the numbered circles reference project numbers from a table on the map, also listed adjacent for convenience):
- Project #6: Goldstream Avenue Improvements (800 Block of Goldstream Avenue at Peatt Road)
- Project #25: Peatt Road (Roundabout Peatt Road at Hockley Avenue)
- Project #26: Peatt Road (Goldstream Avenue to Hockley Avenue)

Additional road dedication, in accordance with ultimate approved design of Peatt Road (including the Hockley Avenue roundabout intersection) was taken at the time of rezoning of the properties on the west side of Peatt Road. Figure 2 below is a snippet of the overall plan view of the approved design (subject to change):

COMMENTARY
Concurrent with the approved frontage works for the developments at 2830 and 2840 Peatt Road (the Terminus and Tallwood 1 buildings now completed), Peatt Road was widened and the majority of the curb for the ultimate road width (for sidewalk and parking scallops) was installed. This has resulted in the utility poles being located within the road top asphalt concrete pavement (ACP). Due to timing, the curb and road widening was completed prior to the ability to decommission the utility poles. Figure 3 highlights the general area where the issue is:

Figures 4 through 8 are representative photos of this area, taken on April 25th, 2023:





The concrete barriers around the base of each pole in the roadway, including construction cones, delineators, and signage are there to protect vehicles from the hazard of these poles now being located in the roadway. The speed of this section of roadway has also been temporarily reduced from 50 km/hr to 30 km/hr and temporary line painting was added to reduce the potential for collisions.
With the poles still in place, the on-street parking scallops and portions of the bike lane are currently unusable, causing problems for both the businesses and residents of the buildings and through traffic, and is an unsightly hazard. The City has received several complaints about this section of roadway; generally with regards to speeding, parking, near misses, conflicts, and collisions.

FINANCIAL IMPLICATIONS
The Developer has used or plans to use (on completed or planned developments within the next couple years) approximately 97% of the DCC credits they have earned to date; therefore, they are no longer willing to accept DCC credits to complete the remaining works. The remaining or outstanding costs should be paid for by the City through the Road DCC Program.
The following costs are based on quotes from 2020. Staff have received confirmation from Telus and Shaw that they are willing to hold these quotes until they receive a response from this report on May 2, 2023. Table 1 lists the total costs by item, the total amounts paid to date, and the outstanding amounts to be paid for the remaining work to be completed. The outstanding amount would have been more, if Telus and Shaw had not contributed $40,000.00 and $43,755.00 respectively for continuance.
If this project does not proceed at this time, the streetscape will remain as is, and the Shaw and Telus quotes will be updated to today’s costs. Quotes will continue to be updated in accordance with inflation and material procurement market prices until the Work is approved to be completed.
Staff are recommending that Council approve this Work to be completed now and add a budget of $355,000.00 (which includes an approximate 5% contingency) to the 2023 Capital Plan in the 2023-2027 Five Year Financial Plan to be funded by Road DCCs. In the event this further increases the deficit currently in the Roads DCC fund, the recommendation would be for the Roads DCC fund to borrow this additional amount from the Parks DCC fund.
Table 1: Undergrounding Outstanding Costs
| Item | Total Costs | Total Paid | Outstanding |
|---|---|---|---|
| BC Hydro | 982,198.30 $ | -982,198.30 $ | - $ |
| Shaw | 131,129.24 $ | -81,160.29 $ | 49,968.95 $ |
| Telus | 127,199.49 $ | -63,969.58 $ | 63,229.91 $ |
| Conduit Undergrounding | 703,790.00 $ | -703,790.00 $ | - $ |
| Change Orders | 102,070.00 $ | -102,070.00 $ | - $ |
| Purchase Orders | 60,000.00 $ | -60,000.00 $ | - $ |
| Telus Live Connections by Chew | 149,000.00 $ | - | 149,000.00 $ |
| Electrical Connections | 75,000.00 $ | - | 75,000.00 $ |
| Total for Undergrounding | 2,330,387.03 $ | -1,993,188.17 $ | 337,198.86 $ |
LEGAL IMPLICATIONS
The entire project will be completed in the City owned road right-of-way.
The City will pay the Utility Company and their Sub-Contractors directly.
OPTIONS
Option 1
THAT Council direct staff to complete the remaining undergrounding Works;
AND
THAT Council approve the inclusion of this project, in the amount of $355,000.00, in the 2023 Capital Plan in the 2023-2027 Five Year Financial Plan to be funded by Road DCCs.
OR Option 2
THAT Council direct staff to not complete the remaining undergrounding Works in 2023.
SUBMITTED BY
Katelyn Balzer, P.Eng., Director of Engineering and Public Works
Concurrence:
Donna Petrie, Senior Manager of Business Development and Events
Concurrence:
Yari Nielsen, Director of Parks, Recreation and Facilities
Concurrence:
Matthew Baldwin, MCIP, RPP, Director of Planning and Subdivision
Concurrence:
Katelyn Balzer, P.Eng., Director of Engineering and Public Works
Concurrence:
Michael Dillabaugh, CPA, CA, Director of Finance
Concurrence:
Marie Watmough, Deputy Director of Corporate Services
Concurrence:
Braden Hutchins, Director of Corporate Services
Concurrence:
Darren Kiedyk, Chief Administrative Officer