Public Hearing / Community Notification Package - File No. 657 Redington Ave (Rogers & TELUS temporary towers)

Applicant notification and public consultation materials for the proposed installation of two temporary telecommunications towers (Rogers & TELUS) at 657 Redington Avenue, including invitation for feedback, comment sheet, site plans, newspaper notices and related resident email correspondence.

Key facts

  • Property: 657 Redington Avenue, Langford, BC
  • Applicants/Agents: Cypress Land Services on behalf of Rogers and TELUS (contacts provided: Tawny Verigin; publicconsultation@cypresslandservices.com)
  • Public Hearing: Tuesday, 19 Feb 2019 at 5:30 pm, Langford City Hall Council Chambers; written comment closing period Feb 25, 2019
  • Proposal: Two temporary telecommunications towers (temporary duration up to six months noted in notices); tower height noted as 20.0 metres in notices
  • Existing cell site to be removed: 2506 Selwyn Road; temporary site required to maintain service

Public Hearing — File No. 657 Redington Ave

Tuesday, 19 February 2019

A Public Hearing to construct a temporary Telus and Rogers antenna at the property located at 657 Redington Ave


Page 3–16

Invitation for Community Feedback

Date: January 16, 2019

ROGERS Site: W4475
TELUS Site: BC3853

Proposed ROGERS and TELUS TEMPORARY TOWER Installations
Located at 657 Redington Avenue, Victoria, BC

Dear Neighbor,

ROGERS and TELUS are in the process of upgrading their network to maintain wireless services to the community. You may or may not be aware, ROGERS and TELUS have an existing cell site located at 2506 Selwyn Road (along the south side of the highway) that includes a monopole tower with antennas. This cell site provides wireless services to all wireless customers in the area. This cell site is scheduled to be removed in early 2019. As such, a replacement cell site is required to maintain wireless service to the area so community members can continue using their mobile devices. To avoid constructing a new stand alone “cell tower”, ROGERS and TELUS will be adding antennas to the new building under construction at 665 Redington Avenue. While the new antenna installation is under construction, ROGERS and TELUS require two TEMPORARY TOWERS to be installed at 657 Redington Avenue to ensure wireless service is maintained to the community. It is expected that these temporary towers will only be required for a short period of time (for a period of less than six (6) months) until the antenna installation on the rooftop is completed. This notification package is an invitation for the public to provide comments regarding the proposed temporary communications towers. ROGERS and TELUS have commenced consultation in accordance with the City of Langford New Transmission Towers Policy No.: 0340-50 Transmission Towers.

PROPOSAL DETAILS:
The property at 657 Redington Avenue is currently vacant and adjacent to a development which includes a four storey rental building at 665 Redington Avenue, Langford, BC. The temporary towers are proposed to be located on the northeast corner of the property (approximate coordinates: N 48.45929°, W 123.49310°). The design includes towers attached to trailers and guyed via concrete blocks. Antenna equipment required to operate the tower is located on the trailer. Preliminary designs are included in this notification for your reference. This is adjacent to Highway 1 (Island Highway). Access will be through the existing property. ROGERS and TELUS confirm that the antenna structures described in this notification package will apply good engineering practices including, structural adequacy during construction. ROGERS and TELUS confirm that the installation is excluded from environmental assessment under the Canadian Environmental Assessment Act. The facility will be built to the National Building Code as well as the BC Building Code. The installation will be in accordance with Transport Canada and NAV Canada requirements. ROGERS and TELUS will each be installing six (6) antennas on the towers. Installation is anticipated to take a week. Please note that the temporary antenna installations will be in full compliance with Health Canada’s Safety Code 6 requirements to ensure public safety.

REGULATORY AUTHORITY
Telecommunication providers are required by Innovation, Science, and Economic Development Canada (ISED), formerly Industry Canada, to consult with the local municipality and the general public regarding new installations. ROGERS and TELUS are committed to meaningful consultation with the City of Langford and the public. The City of Langford has adopted its New Transmission Tower Policy to define Council policy with respect to telecommunication towers and antennas, outline community consultation procedures and to describe municipal expectations with regard to minimizing community impacts from those structures. This letter provides written notification to adjacent landowners and stakeholders with an opportunity to engage in reasonable, relevant, and timely communication regarding this proposal. You have received a copy of this notification package because your property, or a property you have an interest in, is located within 150 metres or less from the proposed installation. The closing period for written comments regarding the proposal is February 25, 2019, however, you can make comments in person at the Public Hearing meeting on February 19, 2019, which begins at 5:30pm at City Hall located at 877 Goldstream Avenue in the 3rd Floor Council Chambers. Any inquiries that are received as a result of this notification will be logged and submitted to the City of Langford as part of our application process.

Aerial photo of the subject property and surroundings
Aerial photo of the subject property and surroundings

Page 3–16

Contacts

Party Contact Details
ROGERS and TELUS (Agents) c/o Tawny Verigin of Cypress Land Services
Suite 1051, 409 Granville Street
Vancouver, BC V6C 1T2
Phone: 1-855-301-1520
Fax: 604-620-0876
Email: publicconsultation@cypresslandservices.com
City of Langford Lauren Morhart, MCIP, RPP — Planner II
City of Langford
2nd floor, 877 Goldstream Ave.
Langford, BC V9B 2X8
Phone: 250-474-6919
Fax: 250-391-3436
Email: lmorhart@cityoflangford.ca
ISED (Vancouver Island Office) 1230 Government Street, Room 430
Victoria, BC V8W 3M4
Phone: 250-363-3803
Fax: 250-363-0208
Email: ic.spectrumvictoria-victoriaspectre.ic@canada.ca (By appointment only)

Page 3–16

Site Plan and Elevations

Site plan for proposed temporary tower locations at 657 Redington Avenue
Site plan for proposed temporary tower locations at 657 Redington Avenue
East elevations — temporary Rogers tower ("Temporary COW") illustration
East elevations — temporary Rogers tower ("Temporary COW") illustration

Page 3–16

Comment Sheet

PROPOSED RADIOCOMMUNICATIONS TOWER
657 REDINGTON AVENUE, LANGFORD, BC
ROGERS SITE: W4475 | TELUS SITE: BC3853

  1. Do you feel this is an appropriate location for the proposed facility?
  • Yes
  • No

Comments:

  1. Are you satisfied with the appearance / design of the proposed facility? If not, what changes would you suggest?
  • Yes
  • No

Comments:

  1. Additional Comments

Please provide your name and full mailing address if you would like to be informed about the status of this proposal. This information will not be used for marketing purposes; however, your comments will only be used by ROGERS & TELUS in satisfying the City of Langford’s “New Transmission Tower Policy”.

Name (Please print clearly):
Email Address:
Mailing Address:

Return to:
Rogers c/o Cypress Land Services Inc.
Suite 1051, 409 Granville Street, Vancouver, BC V6C 1T2
Attention: Tawny Verigin, Municipal Affairs Specialist

Thank you for your input.

Comment sheet / feedback form for the proposed radiocommunications tower
Comment sheet / feedback form for the proposed radiocommunications tower

Page 3–16

Public Notices

Goldstream News Gazette — Wednesday, February 6, 2019

NOTICE OF PUBLIC HEARING

Cypress Land Services Inc., on behalf of Rogers and TELUS, intends to construct two TEMPORARY telecommunications towers at 657 Redington Avenue, Langford, BC for a period of up to six (6) months. All persons who believe their interest in property is affected by the proposed development will be afforded an opportunity to be heard or present written submissions respecting this proposal at a Public Hearing to be held at CITY OF LANGFORD COUNCIL CHAMBERS, Third Floor, 877 Goldstream Avenue, Langford, BC, on Tuesday, 19 Feb 2019, at 5:30 pm. Please be advised that no representations may be received by Council after the close of the Public Hearing and any submissions made to Council, whether orally or in writing, will form part of a public record.

Proposal: To install two TEMPORARY telecommunications towers at a height of 20.0 metres
Applicant: Cypress Land Services Inc. on behalf of Rogers/TELUS
Location: 657 Redington Avenue, Langford, BC as shown shaded on the plan.

Information about the proposed development may be viewed during City of Langford office hours, 8:30 am to 4:30 pm from Monday to Friday (Holidays excluded) and any correspondence for Council may be received until Tuesday, February 19th, at Langford City Hall, 2nd Floor, 877 Goldstream Avenue, Langford, BC, V9B 2X8. Please contact Lauren Morhart in the Planning Department at 250-478-7882 or Tawny Verigin of Cypress Land Services Inc., Agents for Freedom Mobile at 604-620-0877 with any questions on this proposal.

Public notice advertisement — Goldstream News Gazette, Feb 6, 2019
Public notice advertisement — Goldstream News Gazette, Feb 6, 2019

Goldstream News Gazette — Wednesday, February 13, 2019

NOTICE OF PUBLIC HEARING

Cypress Land Services Inc., on behalf of Rogers and TELUS, intends to construct two TEMPORARY telecommunications towers at 657 Redington Avenue, Langford, BC for a period of up to six (6) months. All persons who believe their interest in property is affected by the proposed development will be afforded an opportunity to be heard or present written submissions respecting this proposal at a Public Hearing to be held at CITY OF LANGFORD COUNCIL CHAMBERS, Third Floor, 877 Goldstream Avenue, Langford, BC, on Tuesday, 19 Feb 2019, at 5:30 pm. Please be advised that no representations may be received by Council after the close of the Public Hearing and any submissions made to Council, whether orally or in writing, will form part of a public record.

Proposal: To install two TEMPORARY telecommunications towers at a height of 20.0 metres
Applicant: Cypress Land Services Inc. on behalf of Rogers/TELUS
Location: 657 Redington Avenue, Langford, BC as shown shaded on the plan.

Information about the proposed development may be viewed during City of Langford office hours, 8:30 am to 4:30 pm from Monday to Friday (Holidays excluded) and any correspondence for Council may be received until Tuesday, February 19th, at Langford City Hall, 2nd Floor, 877 Goldstream Avenue, Langford, BC, V9B 2X8. Please contact Lauren Morhart in the Planning Department at 250-478-7882 or Tawny Verigin of Cypress Land Services Inc., Agents for Freedom Mobile at 604-620-0877 with any questions on this proposal.

Public notice advertisement — Goldstream News Gazette, Feb 13, 2019
Public notice advertisement — Goldstream News Gazette, Feb 13, 2019

Notice of Public Hearing (City of Langford posting)

NOTICE OF PUBLIC HEARING

Cypress Land Services Inc., on behalf of Rogers and TELUS, intends to construct two TEMPORARY telecommunications towers at 657 Redington Avenue, Langford, BC for a period of up to six (6) months. All persons who believe their interest in property is affected by the proposed development will be afforded an opportunity to be heard or present written submissions respecting this proposal at a Public Hearing to be held at CITY OF LANGFORD COUNCIL CHAMBERS, Third Floor, 877 Goldstream Avenue, Langford, BC, on Tuesday, 19 Feb 2019, at 5:30 pm. Please be advised that no representations may be received by Council after the close of the Public Hearing and any submissions made to Council, whether orally or in writing, will form part of a public record.

Proposal: To install two TEMPORARY telecommunications towers at a height of 20.0 metres
Applicant: Cypress Land Services Inc. on behalf of Rogers/TELUS
Location: 657 Redington Avenue, Langford, BC as shown shaded on the plan.

Information about the proposed development may be viewed during City of Langford office hours, 8:30 am to 4:30 pm from Monday to Friday (Holidays excluded) and any correspondence for Council may be received until Tuesday, February 19th, at Langford City Hall, 2nd Floor, 877 Goldstream Avenue, Langford, BC, V9B 2X8. Please contact Lauren Morhart in the Planning Department at 250-478-7882 or Tawny Verigin of Cypress Land Services Inc., Agents for Freedom Mobile at 604-620-0877 with any questions on this proposal.

City of Langford public hearing poster/notice
City of Langford public hearing poster/notice

Page 3–16

Correspondence / Public Feedback (Emails and Threaded Messages)

Email Forward from Lauren Morhart to Suzette Chapman

From: Lauren Morhart
To: Suzette Chapman
Cc: Tawny Verigin
Subject: FW: Rogers/Telus Tower concerns - follow up to concerns regarding access to Selwyn Road
Date: Wednesday, February 6, 2019 8:36:57 AM

Hi Suzette,

This is the entire thread.

Lauren

Lauren Morhart, MCIP, RPP
Planner II

From: Lauren Morhart
Sent: Thursday, January 24, 2019 10:08 AM
To:
Subject: RE: Rogers/Telus Tower

Hi ,

To confirm there will be no connection between Redington Avenue and Selwyn Road. There will be an emergency access here, that will be locked and gated unless there is a requirement for emergency personal to access it.

Please let me know if you have any other questions,
Lauren

Lauren Morhart, MCIP, RPP
Planner II

From:
Sent: Thursday, January 24, 2019 9:39 AM
To: Lauren Morhart lmorhart@cityoflangford.ca
Subject: Re: Rogers/Telus Tower

Lauren Morhart,

Thank you for replying but the e-mails were sent by me, , and not my husband, who has no vested interest on Selwyn.

My major concern is that Selwyn Road may permanently become a through road to Redington and this cannot be allowed to happen. It needs to remain closed off at the end of Selwyn Road, as before, and I want assurance from Langford that it will be the case.


Further thread (resident concerns and planner response)

As for the Tower, this eyesore does not belong in this area so close to a family neighbourhood. How about constructing it on the large tract of what is now treed on McCallum across from Costco?

On Jan 24, 2019, at 8:43 AM, Lauren Morhart lmorhart@cityoflangford.ca wrote:

Hi ,

Sorry for the delay. I’ve been away from the office due to illness, however I have reached out to the telecommunication’s agent to confirm access. They will be using the same access as the construction of the buildings on Redington, therefore they will be coming through the existing access off of Redington (through the roundabout) to access the site. The installation of the temporary towers will follow the same construction parking management plan as was issued for the construction of the buildings proposed on Reddington. If your concerns are related to access, primarily, and you wish to obtain more specific answers, I’d have to consult within our engineering department that oversees construction parking and access arrangements for the purpose of construction. If I can answer any of your other questions, I’d be happy to do so.

Lauren Morhart, MCIP, RPP
Planner II

From:
Sent: Wednesday, January 23, 2019 2:59 PM
To: Lauren Morhart lmorhart@cityoflangford.ca
Subject: : Rogers/Telus Tower

Lauren Morhart,

I would appreciate a reply to my e-mail.

Begin forwarded message:
From:
Subject: Rogers/Telus Tower
Date: January 21, 2019 at 12:55:37 PM PST
To: lmorhart@cityoflangford.ca

Lauren Morhart,

(Issues described below in resident email)


Resident email concerning Selwyn Road access (excerpt)

I received the above-noted Proposal in this morning’s mail and, as a concerned homeowner on Selwyn Road where my family resides, I want to know if access to the Tower will be off Selwyn Road. Selwyn has been a family oriented and safe dead end street and it appears that access has already been extended to the housing construction underway and it is totally unacceptable.


Email chain: Roger & Telus Tower at 665 and 657 Redington

From: Lauren Morhart
To: Suzette Chapman
Subject: FW: Roger & Telus Tower at 665 and 657 Redington
Date: Tuesday, February 5, 2019 9:47:11 AM

Lauren Morhart, MCIP, RPP
Planner II

From: Tawny Verigin [mailto:tawny@cypresslandservices.com]
Sent: Tuesday, February 5, 2019 9:43 AM
To:
Cc: ic.spectrumvictoria-victoriaspectre.ic@canada.ca; Lauren Morhart lmorhart@cityoflangford.ca
Subject: RE: Roger & Telus Tower at 665 and 657 Redington

Hi ,

Thank you for providing your comments regarding the proposed temporary communications facilities at 665 and 657 Redington in Langford.

On your comment sheet, you asked about radiation exposure. Please know TELUS and Rogers rely on government experts to set standards for safety. In Canada, Health Canada has established Safety Code 6 to ensure public safety. The limits specified in Health Canada’s SC6 exposure guidelines are based upon review of thousands of peer-reviewed scientific studies of the health impacts of RF energy. SC6 take into consideration the existing EMF energy and the calculations are cumulative to include all surrounding local sites. Should you have further questions regarding the research behind Safety Code 6 regulation or the regulation itself, we encourage those in the community to contact Heath Canada at: ccrpb-pcrpcc@hc-sc.gc.ca.

We appreciate you feedback and will share it with the City of Langford to consider. Should you have further comments or questions please let me know within the next 21 days.

Regards,
Tawny Verigin
Municipal Affairs Specialist
Cypress Land Services Inc., Agents for TELUS and ROGERS

From:
Sent: Monday, February 4, 2019 8:51 PM
To: Public Consultation publicconsultation@cypresslandservices.com
Cc: ic.spectrumvictoria-victoriaspectre.ic@canada.ca; lmorhart@cityoflangford.ca
Subject: Roger & Telus Tower at 665 and 657 Redington

Please find attached my completed questionnaire.

Example resident-submitted comment sheet / questionnaire
Example resident-submitted comment sheet / questionnaire
Additional site access / construction management diagram
Additional site access / construction management diagram