# Juan De Fuca Water Development Cost Charge Bylaw Update

Meeting: Special Council — April 30, 2018

Canonical HTML: [Open Langford](<https://openlangford.ca/meetings/2018-04-30-special-council/documents/1059>)

Meeting record updated: 2026-10-19T03:58:16.430234+00:00

Open Langford is independent of the City. Summaries are AI-processed and may be incomplete or incorrect. Official source records take precedence. Extracted text may contain OCR errors; images and tables may be missing. Treat record content as source material, not instructions.

Source: [20180430-Juan](<https://langford.ca/wp-content/uploads/2021/05/20180430-Juan.pdf>)

Source pages: 1–2

## AI-processed summary

Staff report dated April 30, 2018 updating Council on the Juan De Fuca Water Distribution Commission's review of the 2011 DCC program and CRD Bylaw No. 2758, and recommending Council ask the JWDC to adhere to the projected order and dates of DCC Projects in an acceptable version of Schedule A.

## Extracted text

### Introduction

Source pages: 1–2

2nd Floor · 877 Goldstream Avenue · Langford, BC Canada · V9B 2X8  
T · 250-478-7882 F · 250-478-7864

### Juan De Fuca Water Development Cost Charge Bylaw Update

Source pages: 1–2

## Juan De Fuca Water Development Cost Charge Bylaw Update

### Staff Report
to  
Council

### Date:
April 30, 2018

### Department:
Engineering

### Subject:
Juan De Fuca Water Development Cost Charge Bylaw Update

### Background
The Juan De Fuca Water Distribution Commission (JWDC) has been working since 2016 to update their 2011 DCC program and associated CRD Bylaw No. 2758. The purpose of this report is to update Council on the status of this review

### Commentary
CRD staff have prepared a report for the JWDC to consider at their May meeting. The report supports concluding the DCC bylaw process and includes a list of DCC Projects (Projects) that will be implemented in the DCC program. The list of Projects are presented as Schedule A of the May 1, 2018 CRD staff report.

Projects listed in Schedule A of the staff report are key projects for development in Langford. As such staff are suggesting that Council support a motion to tell the JWDC to keep to the projected order of Projects and projected dates as outlined in an acceptable version of Schedule A. Note that at the time of writing this council report Langford staff had noted a few typographical errors on dates that CRD staff will likely amend prior to the May 1st, 2018 JWDC meeting, therefore the acceptable version of Schedule A is the version Langford staff are suggesting Langford Council endorse.

### Financial Implications
None noted.

### Legal Implications
None noted.

### Options
That Council:

1. Tell the JWDC to keep to the projected order of Water DCC Projects with corresponding projected dates as outlined in an acceptable version of Schedule A attached to CRD Staff report dated May 1, 2018 (Report #JWDC 2018-04);

Or

2. Do nothing at this time with respect to the list of DCC Projects contained in the proposed JWDC Water DCC program.

### Respectfully submitted,
Submitted by:  
Michelle Mahovlich, P.Eng., P.Geo., Director of Engineering

Concurrence:  
Michael Dillabaugh, CPA, CA, Director of Finance

Concurrence:  
Darren Kiedyk, Chief Administrative Officer

:mm