RESOLUTIONS OF THE TRANSPORTATION AND PUBLIC WORKS COMMITTEE – November 21st, 2017
Committee resolutions recommending construction of a continuous middle turn lane on Goldstream Avenue and a multi-year traffic signal controller replacement strategy.
Key facts
- Approve construction of continual middle turnlane on Goldstream Ave (400 to 500 block) at estimated cost $170,000 funded from Gas Tax fund
- Direct staff to upgrade up to four (4) traffic signal controllers in the year and fund from a new Traffic Signal Upgrades capital budget proposed at $150,000 per annum for up to five years
RESOLUTIONS OF THE TRANSPORTATION AND PUBLIC WORKS COMMITTEE – November 21st, 2017
CITY OF LANGFORD
Tuesday, November 21st, 2017
1. Installation of Continual Turnlane 400 to 500 block Goldstream Avenue (Engineering)
That Council approve the construction of a continual middle turnlane in the 400 to 500 blocks
of Goldstream Avenue for an estimated cost of $170,000 funded through the City’s Gas Tax
fund and include this in the 2018 capital budget.
CARRIED.
2. Aging Traffic Signal Infrastructure Replacement Strategy (Engineering)
That Council direct staff to upgrade up to four (4) traffic signal controllers this year and fund this from a new Traffic Signal Upgrades budget contained within the Capital Budget with a proposed budget of $150,000 per annum for up to the next five years or until all aging signals are replaced.