CRD Integrated Water Development Cost Charge Review 2016

Engineering staff report regarding the CRD Integrated Water Services review of Development Cost Charge (DCC) program and recommending a resolution to the Juan de Fuca Water Distribution Board to authorize design works for transmission main and Tank 4 to align with local development and Bear Mountain Parkway works.

4.1 REPORTS a) CRD Integrated Water Development Cost Charge Review 2016

Key facts

  • Subject: CRD Integrated Water Development Cost Charge Review 2016
  • Key infrastructure: Water Pump Station 6 (McCallum Road Pump Station) and Tank 4
  • Bear Mountain Parkway extension (including watermain supply) planned/completed in 2016
  • Recommended action: send resolution to Juan de Fuca Water Distribution Board to authorize design and early 2017 tendering; designs to be funded from DCC reserve
  • Financial/Legal implications: None noted

CRD Integrated Water Development Cost Charge Review 2016

2nd Floor · 877 Goldstream Avenue · Langford, BC Canada · V9B 2X8
T · 250-478-7882 F · 250-478-7864

Page 9–10

Staff Report

To

Council

Date

01/06/2016

Department

Engineering

Subject

CRD Integrated Water Development Cost Charge Review 2016

Page 9–10

Background

The Capital Regional District Integrated Water Services division is undertaking a review of their Development Cost Charge program and associated bylaws. The City of Langford has been part of that review process and has provided information on projected projects that should be included in that program.

Page 9–10

Commentary

Water Pump Station 6 (McCallum Road Pump Station) has been planned for several years now and was pre-serviced with hydro electric power and water supply mains during completion of the Leigh Road Interchange McCallum Road project area in 2013.

Work has advanced since 2013 and the City will be completing the Bear Mountain Parkway extension in 2016. The Bear Mountain Parkway extension includes watermain supply to lands on South Skirt and Bear Mountain development areas. Therefore Water Pump Station 6 (McCallum Road Pump Station) will be constructed immediately with design works already underway and construction tendering is imminent.

Page 9–10

Financial Implications

None noted.

Page 9–10

Legal Implications

None noted.

Page 9–10

Options

That Council resolve to send the following resolution to the Juan de Fuca Water Distribution Board:

WHEREAS the 2011 Juan de Fuca Water Distribution Development Cost Charge Update projected completion of the North Langford (South Skirt) 336m HGL transmission/distribution and North Langford (South Skirt) 228/169m HGL systems by 2021;
AND
WHEREAS an update of the 2011 DCC Report is in progress but will not be completed until later this year;
AND
WHEREAS development of the South Skirt area has commenced;
AND
WHEREAS City of Langford has awarded a contract for the design of the Bear Mountain Parkway for construction in 2016;
AND
WHEREAS services will be most appropriately, efficiently and safely installed during the initial construction phase of the Parkway;
AND
WHEREAS the DCC infrastructure is necessary to efficiently provide domestic service and fire protection early in the development of the South Skirt area;

THEREFORE, BE IT RESOLVED that the City of Langford requests:

  1. That the Juan de Fuca Water Distribution Commission authorize construction of the Pump Station 6 (McCallum Road Pump Station) on acceptance of the design by the CRD, to be funded from the DCC Reserve;
  2. That the Juan de Fuca Water Distribution Commission immediately authorize the design of the transmission main from the McCallum Road Pump Station to Tank 4 (228m HGL) and the design of Tank 4 and associated ancillary works with a view to issuing a tender call for construction early in 2017, to be funded from the DCC reserve and,
  3. That the designs take into consideration the planning projections provided by the City of Langford’s Planning Department to the Consultant updating the Development Cost Charge Report.
Page 9–10

Respectfully Submitted

Submitted by:
Michelle Mahovlich, P.Eng, P.Geo, Director of Engineering

Concurrence:
Matthew Baldwin, MCIP, RPP Director of Planning

Concurrence:
Brent Molnar, Manager of Land Development

Concurrence:
Steve Ternent, Director of Finance

Concurrence:
Jim Bowden, Chief Administrative Officer

/mm