MattersTransportationBYLAW NO. 1728First seen Sep 5, 2017Last discussed Sep 18, 2017
West Shore Parkway road closure
The proposal would close and dispose of part of West Shore Parkway as part of the Parkway completion project, through a land exchange with Glenshire Industrial Park Inc. Closing part of the route could affect access while enabling the project to proceed.
Where it stands: Listed for adoption Sep 18, 2017; no adoption decision is recorded in the provided history.

Background
Earlier and later steps of the same initiative.
Apr 4, 2016
West Shore Parkway Segment 2 contract
The city awarded the West Shore Parkway Segment 2 contract to Windley Contracting for $854,400. A $206,270 watermain provisional is to be paid by Glenshire Business Park Inc.; construction funding includes development cost charges and a federal infrastructure grant.
Apr 18, 2016
Westshore Parkway Segment 8 contract
The work adds a left-turn lane from the Trans-Canada Highway to Westshore Parkway, with related lane, intersection and traffic-signal improvements. Development charges and a federal infrastructure grant fund the project.
May 2, 2016 – Jun 18, 2018
West Shore Parkway Segment 1 construction
The city awarded the West Shore Parkway Segment 1 construction contract to Windley Contracting for $1,353,288 plus GST, with two-thirds of project funding from a federal infrastructure grant. In 2018, it also directed an award for the Parkway sewer lift station, subject to budget, using grant funding for the Parkway completion project.
Jan 22, 2018
West Shore Parkway road closure
The closure removes highway dedication from approximately 0.125 hectares of an unnamed road stub off West Shore Parkway. The bylaw also authorizes the documents needed to complete the closure and disposition.
Timeline
Every time this matter appeared in council records, newest first.