MattersUtilities & InfrastructureFirst seen Nov 4, 2024
Centre Mountain civil works
ApprovedThe City awarded a contract for interim civil works in Centre Mountain Residential Work Packages 2B and 6. The $3,698,571.95 contract, plus GST, is funded through local service area funds.
Where it stands: Construction contract awarded Nov 5, 2024.

Background
Earlier and later steps of the same initiative.
Feb 7, 2022
Centre Mountain water service
Bylaws would establish Centre Mountain water service and residential and business-park roadway local area services, with a separate loan authorization for water works. They provide a framework for local infrastructure and financing; the record gives no cost details.
Jul 18, 2022 – Dec 6, 2022
Centre Mountain water and road borrowing
The City authorized borrowing for water service and residential and business roadworks serving properties in the Centre Mountain local service areas. The borrowing is to be repaid through parcel taxes on the benefiting properties, not by general taxpayers.
Jan 16, 2024
Centre Mountain Phase 1 earthworks
The item concerns a tender award for Phase 1 earthworks at Centre Mountain. The available record does not describe the work or its cost.
Timeline
Every time this matter appeared in council records, newest first.
Colecon awarded $3.7-million Centre Mountain civil works contract
Council awarded the construction contract to Colecon Contracting Ltd. for $3,698,571.95 plus GST funded via LSA funds and authorized the Mayor and CAO to execute the contract.
Decision: Approved awarding the Centre Mountain civil works contract to Colecon for $3,698,571.95 and authorized execution.
Passed 7–0